Hutchisonports Billing Portal / YICT MI — Q Charge (Electricity)
19/11/2026, 02:55:06 GMT+8
← Back to Workflows
YICT MI — Q Charge (Electricity)
[YICT] #6 Q Electricity (Automated) — OSD 'Q' email + ENG table, ESPG/ESPSUR tariffs, supervisor upload, checker confirm
Steps
1
Read OSD Email (subject 'Q')(Email Reader)
in: * → out: lines
2
Read ENG Power Connection Email(Email Reader)
in: * → out: lines
3
Revise PDF Filenames (no Chinese)(Data Transformer)
in: lines → out: lines (replace)
4
Generate CY Information (CY Generator)(Database Query)
in: header → out: lines
5
Fill YICT Upload Template_v3 (ESPG + ESPSUR)(Data Transformer)
in: lines → out: lines (replace)
6
Checker Check ESPG File(Approval Gate)
7
Supervisor Upload MI to nBIS(Database Writer)
in: lines → out: *
8
Checker Confirm MI(Approval Gate)